at a glance
- Full HVAC replacement & sustainability-led refurbishment
- 32 week duration
- On time, on budget
- Achieved SKA Gold rating
- Trading floor remained open throughout
“A fantastic collaborative project, from conception to completion, working with the very best team players to deliver a high-end product in just 32 weeks.”
Justin FelkinDirector
Owen Mechanical & Electrical were appointed to deliver a Design and Build full refurbishment of Sumitomo Corporation’s Level 4 offices at Vintners Place, 68 Upper Thames Street, London. The client required a complete mechanical services upgrade to support modern workplace needs while achieving the highest sustainability standards (SKA Gold).
The works had to integrate seamlessly with the landlord’s new whole-building ventilation strategy and ensure business continuity throughout, as Sumitomo’s trading floor remained live during the phased fit-out.
Our core objectives were to:
OwenME managed the design, engineering, and installation of a new HVAC system, coordinating closely with the client team, landlord CBRE, and main contractor to minimise disruption.
Key Installations
Engineering Challenges & Solutions
Full HVAC replacement & sustainability-led refurbishment | 32 week duration | On time, on budget | Achieved SKA Gold rating | Trading floor remained open throughout
Owen Mechanical & Electrical were appointed to deliver a Design and Build full refurbishment of Sumitomo Corporation’s Level 4 offices at Vintners Place, 68 Upper Thames Street, London. The client required a complete mechanical services upgrade to support modern workplace needs while achieving the highest sustainability standards (SKA Gold).
The works had to integrate seamlessly with the landlord’s new whole-building ventilation strategy and ensure business continuity throughout, as Sumitomo’s trading floor remained live during the phased fit-out.
Our core objectives were to:
OwenME managed the design, engineering, and installation of a new HVAC system, coordinating closely with the client team, landlord CBRE, and main contractor to minimise disruption.
Key Installations
Engineering Challenges & Solutions
“A fantastic collaborative project, from conception to completion, working with the very best team players to deliver a high-end product in just 32 weeks.”
Justin FelkinDirector